Construction Progress Report -
February 2006


View of oxidation ditch

The construction of the Oxford's new wastewater treatment plant by Dewberry & Davis, Inc. is progressing on schedule and on budget. The walls of the new oxidation ditch now tower over surrounding tools and equipment.


Laying 18-inch pipes

Workers continue excavating, laying pipe, and backfilling for the
new 18-inch tertiary drain line from the influent pump station and
for the new 18-inch RAS force main to the oxidation ditch.


Pouring concret for the oxidation ditch

Pouring concrete for the 38th wall of the oxidation ditch.


Construction Progress Updates:

- Early August 2006
- July 2006
- June 2006
- February 2006
- January 2006