Dewberry & Davis, Inc. is working towards final completion of renovations and new construction at the Oxford Wastewater Treatment Plant. They are finishing concrete structures, installing equipment, and running tests on systems at the site. The aerators are now running on the west side of the new oxidation ditch.
Torque tests were successful, and workers are now grading the slopes around the clarifier.
The Parshall flume has been installed at the UV Disinfection structure, where stone is now in place for the base of the control building.
Construction Progress Updates:- Early August 2006
- July 2006
- June 2006
- February 2006
- January 2006
- December 2005