Construction Progress Report -
August 1, 2006!


Running aerator on west side of oxidation ditch

Dewberry & Davis, Inc. is working towards final completion of renovations and new construction at the Oxford Wastewater Treatment Plant. They are finishing concrete structures, installing equipment, and running tests on systems at the site. The aerators are now running on the west side of the new oxidation ditch.


View of ne clarifier

Torque tests were successful, and workers are now grading the slopes around the clarifier.


Placing washed stone for base for UV control building

The Parshall flume has been installed at the UV Disinfection structure, where stone is now in place for the base of the control building.